Description: Replacement of approximately 4,400 feet of 6” water main. The existing water main has broken several times and is in poor condition.
Start Date: Spring 2024
Estimated Completion Date:
Location: S. Glenview Drive
Estimated Project Cost: $424,800
Funding Source: City of Carbondale Utility Fund Revenues, Water & Sewer User Fees
Contractor: TBD
Project Impact: Access to private drives will be maintained throughout the construction process; however, there will be short periods where access may be delayed or prohibited. Water customers in the area should expect minor service interruptions during construction. Specific details on service interruptions will be provided at a later date directly to the affected property owners.
Project Updates:
08/22/2023 - The project is being designed—expected start date early 2024.