North Washington Street Rehabilitation

Description: North Washington Street from Oak Street to Fisher Street has several pavement joints that have failed or deteriorated. This project will replace the pavement joints with concrete patching.

Anticipated Start Date: October 2023

Estimated Completion Date: November 2023

Location: North Washington Street

Estimated Project Cost: $562,000

Funding Source: 100% funded by Motor Fuel Tax revenue

Contractor: TBD

Project Impact: Drivers should expect temporary closures and traffic control during construction. Please seek alternate routes.

Project Updates:

09/18/2023 - Contract with Samron has been executed. 

08/22/2023 - Contract was awarded to Samron Midwest Contracting of Murphysboro, Illinois, for $394,505.

03/14/2023 - Engineering Services Agreement with IDOT