East College Street Bridge/Box Culvert Replacement

Description: Replace deteriorated 14' double box culvert at Piles Fork Creek at East College Street

Anticipated Start Date: Winter 2023

Estimated Completion Date: Winter 2023

Location: East College Street 700 feet east of Wall Street

Estimated Project Cost: 

  • Construction Only: $560,000 
  • Engineering and Construction: $714,000

Funding Source: Surface Transportation Program for Urban Areas (STU) through Southern Illinois Metropolitan Planning Organization (SIMPO)

Contractor: TBD

Project Impact: TBD

Project Updates: 

2/16/2023 - This project is tentatively scheduled to be on the November bid letting. 

8/31/2022 - Project Development Report submitted to IDOT - City now awaiting comments.