Main Street Water Main Replacement - Phase 2 (Completed)

Main Street Water Main Replacement

Description: Replacement of parallel 6” water mains along East Main Street from Cedarview Street to Wall Street. The new 12” water main will provide better water quality and improved fire protection.

Anticipated Start Date: January 2022

Estimated Completion Date: May 2022 

Location: East Main Street from Cedarview Street to Wall Street

Estimated Project Cost: $471,865

Funding Source: City of Carbondale Capital Improvement Program

Contractor: Wiggs Excavating, Inc.

Project Impact: Access to private drives will be maintained throughout the construction process; however, there will be short periods of time where access may be delayed or prohibited. Water customers in the area should expect minor service interruptions during construction. Specific details on service interruptions will be provided at a later date directly to the affected property owners.


Project Updates: 

1/31/2022 - The City of Carbondale has begun work to replace the water main on East Main Street! Construction work is scheduled to be between the hours of 7:00 A.M. and 5:00 P.M. Monday through Friday. Motorists are advised to use caution while traveling in and through this area as there will be lane closures and lane restrictions at various locations along East Main Street from Cedarview Street to North Wall Street.