Southern Illinois Multimodal Station (SIMMS)

Updated SIMMS

WATCH THE PROGRESS!

IMG_1664
IMG_1657
IMG_1655
IMG_1657
IMG_1664
 

Description: The City of Carbondale was awarded $18.3 million in grant funding from the U.S. Department of Transportation's Better Utilizing Investment to Leverage Development (BUILD) program to construct the Southern Illinois Multimodal Station (SIMMS). The grant funds will be used to demolish the existing Amtrak station and design and build the new transportation center in downtown Carbondale. 


View more detailed information on the Southern Illinois Multimodal Station.


Anticipated Construction Start Date: Summer 2023

Anticipated Construction Completion Date: Fall 2024 

 

Location: Downtown Carbondale on the east side of South Illinois Avenue

 

Estimated Project Cost: $26,218,917 

 

Funding Source: $18,321,808 from BUILD Grant, $2,800,000 from IDOT Transit Improvement Program; the City will fund the remaining estimated $5,097,109

 

Contractor: Fager-McGee Construction Inc 

 

Project Impact: TBD

 

 

Project Updates:


02/21/2024 - Masons continue installing CMUs on east elevation.


02/19/2024 - Began installing metal wall framing on the north and west elevations.


02/15/2024 - Metal roof decking continues to be installed.


01/30/2024 - Steel beams are going up quickly. The outside large arched awning is in place, and the steel pyramid ceiling fixture is assembled and soon to be raised. Masons are beginning to lay CMU blocks, and once the blocks are laid, the steel studs, electric, and plumbing will be installed.


12/11/2023 - A portion of the steel beams have been delivered and set in place to be raised this week.


11/20/2023 - The building slab has been poured and is 100% complete.


09/18/2023 - Footings are complete. Fifty percent of the foundation walls are complete.


06/16/2023 - Ceremonial groundbreaking was held. U.S. Senators Dick Durbin and Tammy Duckworth, State Senator Dale Fowler, Illinois State Representative Paul Jacobs, and IDOT Secretary of Transportation Omer Osman were in attendance.


06/01/2023 - The insulation process for the geothermal wells located south of the current Amtrak station was initiated.


05/17/2023 - Following the completion of the demolition, efforts commenced to eliminate the unstable soil present at the construction site.


04/19/2023 - Demolition has begun for SIMMS. We are currently in the process of finalizing the interior colors.


02/16/2023 - The City of Carbondale advertised the bid for SIMMS on November 12, 2022, and accepted and opened bids on January 5, 2023. The Council approved and awarded the contract to Fager-McGee Construction on February 14, 2023, for $23,072,000.

08/15/2022 - Submitted construction documents to Amtrak, FTA, and IDOT  for 100% review.  


06/15/2022 - Submitted construction documents to Amtrak for 90% review.


03/01/2022 - Submitted construction documents to Amtrak for 60% review. 


11/24/2021 - Submitted construction documents to Amtrak for 30% review. 


07/15/2021 - A public meeting is scheduled for Thursday, July 29, 2021, from 4 p.m. until 7 p.m. at the Civic Center. The meeting will allow the public to engage with consultants and offer feedback regarding the final design of the downtown transportation center. 


04/29/2021 - The City of Carbondale selected Design Works and Hmb Architects LLC to design the new downtown transportation center. The design process will include opportunities for the public to engage with the consultants and offer feedback regarding the final design. The City expects a preliminary design for review by the City Council in late 2021. 


12/22/2020 IDOT announced plans to contribute an additional $300,000 to the construction project, raising their contribution to $2.8 million. 


10/21/2020 – MBE plan approved.

 

07/01/2020 – Federal Transit Administration Agreement approved.

 

06/08/2020 – NEPA categorical exclusion granted.

 

11/06/2019 – The City of Carbondale awarded a BUILD grant.